PRE-APPLICATION REVIEW PROCESS
Pre-Application meetings are offered as an informal courtesy* step in the application
process to all citizens, applicants and representatives of applicants. The meeting provides prospective applicants the
opportunity to meet with City staff to discuss a land use proposal before making
a formal application submittal to the City. The purpose of the meeting is to offer
staff advice on the proposal, explain the review process involved in making an
application, and provide handouts, guides and application forms.
*A pre-application meeting is required for requests to change zoning to Planned
Development.
To schedule a Pre-Application meeting, please submit the following documents in
hard copy (no e-mails or faxes accepted) to the City Development Department:
-
Eight copies of a Cover Letter: The cover letter should explain what you wish to do on the property and provide the
name, telephone number and address of the property owner(s), representatives
or agents.
-
Eight copies of a Vicinity Map: A vicinity map showing
where the property is located within the City of Thornton.
-
Eight folded copies of a Sketch
Plan: This graphic should be
drawn to some scale and include a north arrow, date of preparation, building
footprint, parking and landscape areas, access points, streets and
rights-of-way. Also identify any existing buildings on the site, any
natural features of the property which we should be aware of, any
easements affecting the property and what you envision doing on the site
if development were to be approved.
Additional items that would be helpful to our initial reaction to the
proposal include:
-
Building elevations, identifying building materials, types of construction and
setbacks contemplated for the use.
-
Occupancy classification, total square footage, and any subdivision lot
arrangements.
When to make a submittal:
-
The above documents need to be submitted to the City by 12 p.m. on Tuesday of
any week
to schedule a meeting for the following week on
Thursday. If all meeting times are already reserved, the meeting will
be scheduled for the next available date and time, typically two weeks out on
Thursday.
-
The specific date and time will be assigned for your meeting when we receive your
submittal.
At the meeting:
-
You are welcome to bring anyone you wish to the pre-application meeting to take notes or raise
related questions that might be considered.
-
You will be introduced to the Case Manager in Current Planning and the Project Manager in
Development Engineering who will be assigned to your case(s) if you decide to
proceed to making any formal submittals. Staff is advisory only. Decisions on
what should be done for the submittal are made by the applicant.
If you have any questions, please feel free to call the City Development
Department at 303-538-7295.